Bristol Airport AGL-Workstream 2
The works were completed in 5-hour working windows over a 4-month period.
ClientBristol Airport
January 2024 - April 2026
This project incorporated the provision of Aeronautical Ground Lighting system (AGL) equipment and cables for the AGL resilience upgrade works at Bristol Airport.
The works were completed in 5-hour working windows over a 4-month period.
The project included:
Replacement of all transformers and joints on the whole airfield, both runways and taxiways
Supply and Installation of 1,400 Isolation Transformers, Pit furniture, earth bars and earthing within 200 Pits
Saw cutting and sealing new Secondaries for the Approach 27 inset lights
Supply and installation of all elevated and inset lights for the 27 Approach installed on existing Excel approach masts
Coring in new Seating cans for the new Inset Approach light fittings
Commissioning all circuits and CCRs to allow for the new circuit Loads.
Each shift required the locking off all circuits with Bristol Airport AGL Engineers.