RAF Valley AGL Refurbishment

As part of the AOS Framework, LAML delivered the AGL refurbishment for RAF Valley’s secondary runway.

Client: RAF Valley

Contract Dates: October 2024 - October 2025

As part of the AOS Framework, LAML delivered the AGL refurbishment for RAF Valley’s secondary runway, supporting Lagan Aviation & Infrastructure.

Works included:

  • Upgrading all runway, taxiway and approach lighting to LED,

  • Installing over 700 transformers,

  • New CCR, MCS and termination panels delivering all associated M&E within the new substation.

The project also included a CL2B approach system, replacement of wing bars and IRDMs, and an MCS upgrade to support the modernised AGL infrastructure.

Summary of activities:

  • M&E Fit Out B2a & B2b New Lighting Protection System to B2a & B2b -2nr Installation of CCRs

  • New AGL Cable Termination Panels

  • AGL LED Lighting Upgrade& Airfield Signage Installation of IRDMs

  • MCS Modifications & upgrade & new TL48s & D20s

  • Installation of AGL 6mm Earthing - 32,500m Static Earthing Installation to ASP1 -1nr

  • Installation of new Seating Pots – 401nr

  • Replacement of 019 Approach Masts

  • Installation of new Primary Cabling – 55,000m

  • Installation of new 2core 4mm Secondary Cabling -16,000m

  • Photometric Testing 19/01

  • Runway Flight Calibration Check